OEE Calculator

Enter one shift and see where the time went, in minutes and parts.

Time (min)
Parts
Results update as you type.
76.0%Typical performance
⁦115⁩ of ⁦480⁩ planned minutes were lost. World-class is 85% or more.

Results

Free with an account
OEE (Overall)76.0%−⁦9.0⁩ vs ⁦85⁩
Availability89.2%−⁦0.8⁩ vs ⁦90⁩
Performance88.8%−⁦6.2⁩ vs ⁦95⁩
Quality (FPY)96.1%−⁦3.8⁩ vs ⁦99.9⁩

Where the 480 minutes went

Planned time without breaks: fully productive time and the three losses.
LossMinutesParts% of time
Downtime52.0≈ 520 not made10.83
Speed48.0≈ 480 not made10.00
Quality15.0150 rejected3.13
What to work on firstPRO
Pro shows which loss to tackle first in this shift, and how to start.

About the OEE calculator

How it is calculated · worked example · references

What it does

Overall Equipment Effectiveness (OEE) shows how much of the planned production time turned into good parts at the ideal speed. It splits the loss into three: Availability (the machine stopped), Performance (it ran slower than the ideal cycle) and Quality (it made parts that were not good first time). The calculator also turns each loss into minutes and parts, so you can see where the time went and which loss to attack first.

Method

OEE follows the definition of Nakajima and the Japan Institute of Plant Maintenance (TPM), and the result is compared with the world-class levels for each factor. The calculation is tested against a published worked example.

Worked example

The data behind “Try an example”: an 8-hour shift (480 min), 52 min of unplanned stops, ideal cycle 6.0 s, 3,800 parts made, 3,650 good.

ResultValueLoss
Availability89.17%52 min stopped
Performance88.79%48 min of slow running
Quality96.05%150 parts (15 min)
OEE76.04%Typical, room to improve

The two biggest losses, stops and slow running, are almost equal, so both are worth a look before quality.

References

  • Nakajima, S., Introduction to TPM: Total Productive Maintenance.